Phase I
Requirements to safely re-open the aquatic center:
· ADA Upgrades: $$50,001
· HVAC & Plumbing: $$879,750
·Pool Replacement: $2,600,000
· Site Work: $349,460
· Indirect Costs: $515,063
· Total: $4,444,263
_edited.jpg)
Phase II
2-5 Year Improvements · Architectural: $308,851
· Civil: $804,107
· Electrical: $46,763
· Mechanical: $156,404 · Plumbing: $454,991
· Structural:$51,109
· Total Phase II: $1,822,225

Phase III
6-10 Year Improvements
· Architectural: $2,269,561
· Electrical: $86,935
· Structural: $59,081
· Indirect: $3,264,884
· Total Phase III: $5,680,461
Total Project · $11,946,949